Project Name: CONSTRUCTION SUPERVISION FOR ROAD PARALLEL TO ZIYA BUNYADOV BOULEVARD STARTING FROM HASAN ALIYEV STREET (OLYMPIC STADIUM ROADS)-PHASE 2

Country: Azerbaijan

Finance Source: Government Funded

Tags: Azerbaijan, Local, Transport, Supervision

Detailed Narrative Description of Project:

The First European Games that The Opening Ceremony held on Friday 12 2015 took place in the City of Baku, Azerbaijan. Because of the European Games a new Olympic stadium was constructed. The government’s ambitious plans to develop this area after the European Games was finished are continuing and the new roads are planned surrounding the stadium area as well as the reconstruction of the existing roads connecting to the new roads.
The road in the area would meet modern standards. The total length of the 2×3 lanes new road is 4 kilometers (Category 1 in accordance with international standards). There are 1 bridge with 30 spans of 965 meters in length and 1 underpass of 58 meters in length for vehicle traffic along the road.
Total construction cost: 214,536,091 USD

Detailed Description of Actual Services Provided by TEMELSU:
• Overall technical and administrative management of the contract
• Checking the Shop Drawings submitted by the Contractor
• Supervision of construction and ensuring the quality required (FIDIC Compatible Contract)
• Control and appraisal of progress and reporting
• Determining the value of approved variations and fixing new rates subject to limitations of authority.
• Issuing payment certificates
• Issuing Completion and Defects Liability Certificates
• Ensuring implementation of Environmental, health and safety and traffic management measures
• Advising the Employer on all matters related to the execution of the contract
• Verification of “As-built” drawings supplied by the contractors