Project Name: Feasibility and Final Design of Bisha, Aqiq, Murwani and Ranyah Dams

Country: SAUDI ARABIA

Finance Source: Government of Saudi Arabia

Partners:
Zuhair K.Yassin

Tags: Saudi Arabia, Local, Feasibility, Design

TEMELSU prepared feasibility studies, final designs, technical specifications and tender documents for these four dams and all the hydrological and geological studies were undertaken by the specialists of TEMELSU. Aqiq Dam was commissioned in 1986 and since then it is in operation for water supply to Al-Baha City. The construction of Bishah dam has been completed in December 1996.

 

 

Project Name Dam Type Height From Foundation (m) Volume of Dam

Body (m3)

Purpose

 

Bishah Dam Concrete gravity 113 1 500 000 Flood control, Recharge, Irrigation
Aqiq Dam Concrete gravity 44 82 000 Water Supply
Murwani Dam Earth and rockfill 100 6 000 000 Flood control, Recharge
Ranyah Dam Concrete gravity 38 82 000 Flood control, Recharge

 