Project Name: SUPERVISION OF CONSTRUCTION WORKS FOR SABUNCUBELİ TUNNEL
Country: Turkey
Finance Source: Commercial Credit
Tags: Turkey, Local, Transport, Supervision
Detailed Narrative Description of Project:
The Project is PPP model (Public Private Partnership) construction, operation and transfer of the section (named Sabuncubeli Tüneli) from Km 9+400 to Km 15+900 of İzmir – Manisa Highway. The brief description of the segment is as follows:
• The length of the road: 6.500 m.
• Number of tunnel : 1 (twin tubes)
• The length of tunnel: 4.070 m.
• Number of bridge : 1 bridge
Detailed Description of Actual Services Provided by TEMELSU:
• overall technical and financial administration of the contract;
• approval of the contractor’s work program and sources of materials;
• approval of the detailed design and contractor’s working drawings;
• construction supervision of the works;
• control and appraisal of the progress of the works;
• ordering tests of materials and of completed works;
• ordering the removal of improper or substandard works;
• ensuring that environmental mitigation measures are implemented during construction and as permanent works are brought into use;
• ensuring that traffic and safety requirements (including on-site movements) are met;
• verification of “As-built” drawings supplied by the contractor, advising the Employer on all matters related to the execution of the contract.